How COVID Changed Factory Solar Economics

Before I get into it, let me throw a number at you. My last factory’s electric bill in March 2020 was £24,378. By July 2021, it was £36,712. Nearly a 50% jump in just over a year. That’s the kind of spike that makes you rethink everything about your energy strategy, especially solar.

Look, I’ve managed three major solar installations for factories over the past decade. Each one taught me something new. But the pandemic? It flipped the script. COVID impact factory solar economics in ways nobody expected. If you’re still working off pre-pandemic assumptions, you’re probably looking at quotes that are 20-30% too high, or worse, missing the mark entirely.

Why COVID Changed the Equation

First off, the pandemic messed with supply chains like nothing before. Solar panels, inverters, mounting hardware - everything got delayed. I remember waiting four months for a batch of Canadian panels back in early 2021. What was supposed to be a 6-week lead time stretched out because of factory shutdowns in Asia and shipping bottlenecks. That delay meant higher installation costs and pushed ROI timelines back.

And it wasn’t just delays. Prices for raw materials skyrocketed. Polysilicon, copper, aluminium - all critical to solar gear - saw 30-40% price hikes in 2020-21. Suddenly, a system that was quoted at £112,456 in January 2020 ended up costing £147,892 by mid-2021. That’s a real hit to budgets.

Energy costs COVID factory-wise went through the roof too. Not just because of demand but also changes in grid pricing structures. Some factories saw peak rates increase by 15-25%. That’s where solar started to look better. The math shifted to favour onsite generation more than ever.

Installation Realities During the Pandemic

You might think with all these challenges, rushing into pandemic solar installation projects would be a bad idea. But here’s what happened on the ground.

Factories that moved forward last March or April 2020 often had to adapt on the fly. Labour shortages meant crews worked in smaller teams. Safety protocols slowed down the work. But on the flip side, less factory production meant rooftops and yards were more accessible for equipment and panels. Some installations finished ahead of schedule because of that.

One installation in the Midlands I oversaw hit a snag because the local council’s planning office was closed. That pushed permits from 6 weeks to 3 months. Cost? About £6,500 in project management fees alone. Delays like this are why you need a contingency budget of at least 10%.

ROI in a Changed World

Return on investment is the bottom line. Before COVID, a 250kW system typically took 4-5 years to pay back through energy savings and incentives. Post COVID? That timeline stretched to 5-6 years in some cases due to higher upfront costs.

But here’s the kicker. Energy cost inflation meant actual savings post-installation were bigger than expected. One factory I worked with saw their annual savings jump from £21,000 pre-pandemic estimate to £28,500 the year after installation because grid energy prices kept climbing.

Here’s a real quote from that project: “Initial estimates pegged payback at 5 years – now we’re looking at closer to 4.2 years thanks to energy price hikes.” That’s a big deal.

Government Incentives and Financing Post-COVID

Government programs adapted too. The Feed-in Tariff wound down in 2021, but new grants and loans popped up. The UK’s Industrial Energy Transformation Fund offered up to £150,000 for energy efficiency projects, including solar. I’ve seen factories snag £72,500 towards a £290,000 system, knocking the out-of-pocket down considerably.

Financing options became more creative. Some vendors started offering performance-based contracts where you pay monthly commercial solar systems based on power generated. That’s helpful if capital is tight post-pandemic.

One factory I advised used a green loan from their bank with a fixed 3.4% interest rate over 10 years. The total repayment was about £325,000 for a 400kW system, but energy savings and incentives brought net costs down to £210,000. It’s complicated math but worth crunching.

Maintenance and Operational Integration: What Changed?

Look, solar isn’t just about panels and inverters. You need to keep it humming, especially in a factory setting.

COVID restrictions meant some maintenance visits got delayed. We had a case where a fault in the inverter went unnoticed for nearly 3 months because the service team couldn’t access the site. That cost the factory about £4,500 in lost generation, plus a £1,200 repair bill.

Operational integration also shifted. More factories adopted remote monitoring systems, partly because engineers couldn’t always be onsite. That added about £5,000 upfront but saved headaches later.

Common Mistakes That Cost Real Money

Here’s what I saw go wrong more than once:

    Accepting quotes without detailed breakdowns. One quote came in at £134,567 with no clear cost split. Turns out, £25,000 was for imported Chinese panels that didn’t meet local standards. I’m not anti-Chinese panels – some are fine – but you need to vet specs carefully. Ignoring site-specific factors. One factory’s roof wasn’t properly assessed. After installation, shading from a new HVAC unit dropped output by 18%. That’s £3,200 a year in lost savings. Skipping contingency budgets. Delays and cost overruns added 13% extra on average to pandemic installations I reviewed.

Vendor Selection: What I Learned

Don’t just pick the lowest bid. Pick vendors who understand factory operations. One vendor I worked with had a track record with pharmaceutical plants and knew GMP compliance issues. That saved the client £12,000 in paperwork and rework.

Look for vendors who offer transparent timelines. If they promise a 3-month install but can’t guarantee permits or supply chain delays, get that in writing.

image

And ask about post-installation support. Some vendors dropped off after handover. That left factories scrambling for service contracts at premium prices.

Case Study: Midlands Factory Solar Project

System size: 350kW

Total cost: £296,800

Government grant: £72,500

image

Financing: 10-year green loan at 3.4%

Installation timeline: 5 months (including permit delays)

Energy savings year 1: £27,800

Payback estimate: 5.1 years

Lessons learned: Factor in local planning delays and push for remote monitoring from day one. Maintenance delays cost £2,300 in lost generation during the first year.

Industrial Solar Post COVID: What’s Next?

Supply chains have loosened up but prices haven't dropped back to pre-pandemic levels yet. Expect material and labour costs to stay elevated for at least the next 12-18 months. Energy costs will keep climbing too, so solar remains a strong hedge.

More factories are exploring hybrid solutions - solar plus storage or solar plus demand response. That’s where the real money is in the future.

But don’t get caught out chasing shiny tech without solid ROI calculations. I’ve seen proposals for £450,000 systems with storage that don’t pay back in under 10 years. That’s a bad deal.

Bottom Line

COVID impact factory solar economics in ways that forced everyone to rethink timelines, budgets, and ROI. If you’re working on a pandemic solar installation or planning one now, don’t trust old numbers or assumptions.

Get detailed quotes. Account for supply chain risks. Factor in higher energy prices. Use government incentives smartly. And pick vendors who know factory operations like the back of their hand.

Done right, solar still pays off big time. Done wrong, it’ll cost you tens of thousands and years of headaches.

FAQ

Q: How has COVID impacted solar panel prices for factories?

A: Prices increased by roughly 30-40% during 2020-21 due to raw material shortages and supply chain disruptions. While some costs have stabilized, prices remain above pre-pandemic levels.

Q: Are installation timelines longer post-COVID?

A: Yes. Expect delays of 1-3 months longer due to permit backlogs, labour shortages, and shipping delays. Factories should build contingencies into their schedules.

Q: How do energy cost increases affect solar ROI?

A: Higher energy prices improve solar ROI by increasing the value of generated power. Although upfront costs are higher, payback periods may remain similar or even shorten.

Q: What financing options are available for factory solar now?

A: Beyond traditional loans, performance-based contracts and green loans with low fixed rates have become more common. Government grants can also reduce upfront costs.

Q: Should I worry about panel origin given supply chain changes?

A: Not all Chinese panels are bad, but quality varies. Vet vendors carefully and demand detailed specs and warranties. Local standards compliance is crucial.

Q: What maintenance challenges arose during the pandemic?

A: Restricted site access delayed repairs and inspections, leading to lost production. Remote monitoring systems have become essential to catch issues early.

Q: How can I avoid cost overruns in pandemic-era solar projects?

A: Insist on detailed quotes, include contingency budgets (10-15%), verify site-specific conditions, and plan for possible permit and supply delays.

Q: Is solar still a good investment for factories post-COVID?

A: Yes. Despite higher costs, rising energy prices and new incentives maintain solar’s appeal. Smart planning and vendor selection are key to success.